Engineering Validation for Tulkaram wastewater collection System Improvement
The primary objective of this project is to review and validate the previous design work done by Black & Veatch for various improvements to the wastewater collection system and roadways in Tulkarem, West Bank. The main focus of this activity is to update the RFTOP documents in preparation for a tender process during 2022.
The scope of the proposed improvements includes the following:
- Construction of 12 km of new gravity sewers within the Tulkarem area.
- Expansion of the existing Irtah Pump Station (IPS).
- Installation of a new 3 km force main for the IPS.
- Development of a screening and flow metering facility at the oxidation ponds.
- Rehabilitation of 3 km of roads along the IPS force main, specifically Roads 1-4.
Services:
The project includes validation services for:
- 12 km of new gravity sewers in Tulkarem
- Expansion of the existing Irtah Pump Station (IPS)
- New 3 km force main for the flow metering facility at the oxidation ponds
The specific tasks involved are:
- Design Review Memorandum
- Updated Drawings and Specifications
- Review of Existing Utilities
- Confirmation of Required Electric Service
- Verification of Permits and Approvals
- Update of RFTOP and Bid Ready Package