JERICHO WASTEWATER
The Jericho Wastewater Collection System Expansion Phase 1B includes of the following infrastructure development:
- Construction of approximately 500 m force main
- Construction of approximately 20 km sewer pipelines
- Construction of approximately 3.5 km service laterals
- Construction of approximately 719 manholes
- Construction of approximately 755 connection pits
- Construction of a lift station.
- Milling and overlay of approximately 4.5 km of roads with concrete protection at both sides.
Assignment included:
Construction supervision and Contract administration Cost, time, and quality management.
Coordination with relevant stakeholders and authorities. Reporting Quantity takeoff measurements and approval of payments. As built drawings, operational manual and closure of the project.
Clients
USAID
Location
Jericho – Palestine
Service
Construction Management
Prime Consultant
AECOM
Contractor
Saqa Skills & Quality Construction
Owner
Palestinian Water Authority